Hi All,
This is Process industry with planning strategy 52 for our final product. We maintain PIR for our Finished goods. Our problem here is, due to insufficient component or lack of machine/labor shop-floor didn't produce as much qty as per the Sales Order's qty with specific delivery date. Planner expect, the sales person should adjust the SO delivery date based on material's next available date. Shop floor as well logistic person would like to know about the availability of the material for delivery.
We maintain planning strategy as 52 for header material
maintain PIR with req type as VSE
Availability check as 02
Requirement type in SO is KSVS
Our requirement is more similar to this
What is the Sales Order ATP exception process for Strategy 52?
But, still not clear. Our Main intention here is, as per existing plan, shop floor couldn't execute their planing due to lack of machine/material or breakdown , etc. So, sales person should adjust the sales order delivery date as per the next available date by doing Re-Availability check in SO. What is the best practice to handle this scenario? Any suggestion please.
Thanks