Hello
See question 6 of the FAQ note 550568:
6. Question:
There are several requirements on one day. Is it possible that the
MRP creates a separate procurement proposal for every requirement?
Answer:
Same as for the daily lot size with a number of periods = 1 (lot
size TB), requirements of one day are also grouped into one
procurement proposal for the lot-for-lot order quantity (lot size
EX) (see documentation for the lot-for-lot order quantity). Separate
procurement proposals can be achieved only if you work with
make-to-order production. Here, the requirements are managed in
separate planning segments of the stock/requirements list.
BR
Caetano